METS is back in full glory

The world’s largest marine equipment trade show is back in full glory with thousands of industry professionals gathered from around the world to showcase their innovations, products and trends.

Continue reading

Marina Polesana

In April 2022, the first phase of the construction of Marina Polesana in Pula was completed. It is one of the largest nautical-tourism projects on the Adriatic, which is realized by the company Kermas Istra in the former Katarina Monumenti military zone.

The marina covers more than ten hectares of land, which includes 304 berths, of which 262 are in the sea and 42 on land. 
In the second phase of this project, in the quarry the construction of a hotel and about 900 moorings on land and 150 at sea are planned.

In the first phase of this project, Marinetek Adriatic delivered 31 pieces of PREMIER Pontoons and 28 pieces of HEAVY DUTY pontoons, i.e. 970 meters of pontoons with anchoring systems of jetties, access bridges, mooring cleats and various equipment were made and installed.

DJI_0477DJI_0477
DJI_0561DJI_0561
DJI_0563DJI_0563
DJI_0564DJI_0564
DJI_0566DJI_0566
Marina-Polesana3Marina-Polesana3
polesana86-050422polesana86-050422
untitled14-100222untitled14-100222
polesana_aerial13-120422polesana_aerial13-120422
polesana_aerial1-120422polesana_aerial1-120422
polesana_aerial3-120422polesana_aerial3-120422
polesana_aerial12-120422polesana_aerial12-120422
polesana_aerial18-120422polesana_aerial18-120422
polesana86-050422polesana86-050422
polesana87-050422polesana87-050422

TECHNICAL CHARACTERISTICS

Project:
Marina Polesana
Location:
Pula, Sv. Katarina
Capacity:
262 berths
Works:
construction and installation of piers with anchor systems
Budget:
29 mil kn
Date of completion:
2022. (first phase)
Products:
Premier and Heavy Duty pontoons

Traditional nautical fair

This year’s Biograd Boat Show confirmed its position as the best Croatian nautical fair and proved itself as one of the most important fairs in the Mediterranean.

Continue reading

Port Račišće

After the Porto UŠ project, where Marinetek Adriatic delivered pontoon docks for a total of 99 berths for the local population for the port authority of Korčula, successful cooperation has continued with the plan to organize the communal part of the Port of Račišće.

The contract for this project was signed in September 2021, and three months later, the complete pier, which constitutes the first phase of the work, arrived in Račišće. The total length of the pier is 48 meters and it is used for mooring about 30 boats.
As part of the second phase of the work, the existing docks were re-arranged and a new anchoring system was installed, so that at the end the port of Korcula Račišće got 74 completely new moorings arranged.

Račišće 1Račišće 1
RačišćeRačišće
Račišće2Račišće2

TECHNICAL CHARACTERISTICS

Project:
Port Račišće
Location:
island of Korčula, port Račišće
Capacity:
74 berths
Works:
construction and installation of piers with anchor systems
Budget:
2 mil kn
Date of completion:
2022.
Products:
M3316BRK

Port Novalja

The works for the Port Authority of Novalja, on the island of Novalja were completed at the beginning of June 2022. Marinetek Adriatic built and installed two floating pontoon piers in Novalja which provided around 160 permanent and seasonal moorings for the vessels of the local population. 

The works were completed in two phases, and new floating elements will protect the ships even in case of severe weather conditions an large waves. Marinetek installed a 40-meter floating breakwater with a width of 5 meters for the first time in Croatia. Also 380 meters of strong Premier pontoon elements were installed to form the floating jetties.

novaljanovalja
novalja2novalja2
novalja3novalja3

TECHNICAL CHARACTERISTICS

Project:
Port Novalja
Location:
Novalja, Island of Pag
Marina capacity:
160 berths
Works:
construction and installation of piers with anchor systems
Budget:
5.8 mil kn
Date of completion:
2022.
Products:
M2712PE, M5320BRK