The works for the Port Authority of Novalja, on the island of Novalja were completed at the beginning of June 2022. Marinetek Adriatic built and installed two floating pontoon piers in Novalja which provided around 160 permanent and seasonal moorings for the vessels of the local population.
The works were completed in two phases, and new floating elements will protect the ships even in case of severe weather conditions an large waves. Marinetek installed a 40-meter floating breakwater with a width of 5 meters for the first time in Croatia. Also 380 meters of strong Premier pontoon elements were installed to form the floating jetties.
TECHNICAL CHARACTERISTICS
Project: | Port Novalja |
---|---|
Location: | Novalja, Island of Pag |
Marina capacity: | 160 berths |
Works: | construction and installation of piers with anchor systems |
Budget: | 5.8 mil kn |
Date of completion: | 2022. |
Products: | M2712PE, M5320BRK |